Utility

John Warner

Utility Division Manager

Luke Weinstein

Project Manager/Estimator

Jeff Dahlen

Project Manager

Town of Marana – WRF Sand Filter Media Replacement

As part of a Job Order Contract, KE&G removed and replaced 324 tons of media from Parkson’s Sand Filter beds. Upon media removal, the facility process inspection revealed needed repairs to media hoppers and up-lift air pumps.

PROJECT OVERVIEW

Location : Town of Marana
Type : Sand Filter
Delivery Method : Utility
View Project

Tangerine Booster Station

Construct a new booster station to service planned future expansion for Town of Marana. Station comprised of two 50-hp and two 10-hp pumps for residential water service and one 60-hp pump to support fire flow requirements. Two 5,000-gallon hydropneumatic tanks were installed to regulate pressure; electrical and controls systems located under a steel shade structure;… Continue reading Tangerine Booster Station

PROJECT OVERVIEW

Location : MARANA
Type : MARANA BOOSTER STATION
View Project

Patagonia WWTP Upgrades

Patagonia’s 110,000 gallons per day Wastewater Treatment Plant required rehabilitation of critical components and improved process efficiencies to reduce ever-increasing operating costs. Major repairs and upgrades to the facility were completed during a 110-hour operational bypass period.

PROJECT OVERVIEW

View Project

Snyder Hill PS Forebay Rehabilitation

The SHPS Forebay Reservoir is the gateway for water from the CAP system into Tucson Water’s distribution; 80% of Tucson’s water flows through this structure. The rehabilitation included removing and disposing of the reservoir’s existing aluminum roof and CSPE liner, as well as miscellaneous concrete repairs and structural steel additions; epoxy coating of exposed concrete;… Continue reading Snyder Hill PS Forebay Rehabilitation

PROJECT OVERVIEW

View Project

Escalante Reservoir Rehabilitation

This 10-million-gallon reservoir had a very similar scope to the SHPS Forebay project. It required demolition of the existing roof and installation of a new standing seam aluminum roof, coating of exposed concrete, and installation of a new CSPE liner system. Approximately 50 tons of new steel framing was also installed to meet current structural… Continue reading Escalante Reservoir Rehabilitation

PROJECT OVERVIEW

View Project

Anamax Park Sewer Extension

This project was developed to expand the Anamax Park sewer capacity and future development. KE&G installed 1,420 feet of new 8-inch sewer and 842 feet of new 4-inch services, this included 6 new 48-inch diameter manholes. After ADEQ approval, we abandoned three septic tanks and tied the new system to existing Pima County Sewer system.

PROJECT OVERVIEW

Location : SAHUARITA
Type : SAHUARITA SEWER REPAIR
View Project

La Estancia Transmission Phase 1

KE&G constructed Phase 1 of a 2-phase project consisting of installing 1,160 feet of new 24-inch, 16-inch, 12-inch, and 8-inch water lines. 342 feet of the new 24-inch line was installed using the jack and bore method under I-10 with a 42-inch casing including a new gate and butterfly valves.

PROJECT OVERVIEW

Location : TUCSON
Type : TUCSON WATER INSTALL
View Project

Water Main Repair at Central Avenue

KE&G responded to an emergency repair on a 24-inch CCP and 6-inch CA water main. The repair included welding flanges onto the existing pipe, new 24-inch DIP, a new hydrant, and approximately 515 feet of new 8-inch DIP. Night work was coordinated to lessen the impact on the area businesses and pedestrians.

PROJECT OVERVIEW

Location : TUCSON
Type : TUCSON WATER REPAIR
View Project

Wildflower Outfall Sewer

KE&G completed a 2.5-mile outfall sewer. The system was an 18 to 24-inch installation at 18+-foot depths with 18 new manholes measuring 60 to 72-inches in diameter. This was a private development funded project for PCRWRD receivership.

PROJECT OVERVIEW

Location : TUCSON
Type : TUCSON SEWER REPAIR
View Project

WANT TO WORK WITH US?

KE&G is a respected 100% employee-owned company that is committed to delivering safe, high-quality projects that exceed the expectations of our clients

Connect