La Estancia Transmission Phase 1

KE&G constructed Phase 1 of a 2-phase project consisting of installing 1,160 feet of new 24-inch, 16-inch, 12-inch, and 8-inch water lines. 342 feet of the new 24-inch line was installed using the jack and bore method under I-10 with a 42-inch casing including a new gate and butterfly valves.

PROJECT OVERVIEW

Location : TUCSON
Type : TUCSON WATER INSTALL
More Projects

WANT TO WORK WITH US?

KE&G is a respected 100% employee-owned company that is committed to delivering safe, high-quality projects that exceed the expectations of our clients